“On the progress of work to complete the construction of problematic objects in the framework of the program” Nyryly zher “
During the weekly weekly meeting under the chairmanship of Astana akim Aset Isekeshev, the issues of equity participation in housing construction were discussed.
The first deputy akim of the city of Astana, Sergei Khoroshun, reported to the akim on the progress of work on the completion of the construction of problematic facilities in the city within the framework of the “Nurly Zher” program.
“Authorized body for the completion of construction of problem objects – LLP” Elorda Kurylys Kompaniyasy “today is working with the 23 problematic objects recommended at the meetings of the Interdepartmental Commission (objects of the company LLP” ISK “ASI” – LCD “Shygys” and “Zhagalau” residential complexes “ABC housing” apartment complexes “My peaceful home”, “Baspana”, “Arystan”, “Turan Syganak”, “Capital-2” and others), “- said Khoroshun.
According to him, for the execution of orders entered into a loan agreement with JSC “Baiterek Development” in the amount of 40 billion tenge for the period of 4 years from the payment of semi-annual payments of remuneration in the amount of 0.4% per annum. At the moment, the first tranche of KZT4 bn. Has been received.
May 2, 2018 signed the first agreement on joint activities to complete the construction of LCD “Shygys”, residential group 3B. The authorized organization considers the issue of signing agreements on joint activities in the near future for seven facilities of residential complexes “Shygys” and “Zhagalau”.
“However, in the current year it is planned to enter into a contractual relationship for another 15 residential complexes problem recommended by the interdepartmental commission, with the total number of shareholders 7381 people”, – he said.
The following work is carried out for all problematic objects:
on objects where there are conclusions of financial and technical audit and positive conclusion of state expertise, work is underway to prepare a financial model (financial analysis) to ensure the economic feasibility of projects;
development of design and survey works and design estimates;
determination of the possible construction of additional residential areas on allocated land plots;
constant explanatory work with co-investors and participants of HBC.